April 9th Update
- Brick and Stone is complete except for the piers
- Shingles are complete except for the canopies
- Windows are installed except for the round windows over the altar
- EFIS is starting – Water Proofing coat done 04/09
- Underground Storm Drainage
- Piers for the columns are being formed at main entrance
- Canopy Drop off is being framed
- Site paving will start week of 04/13 weather permitting
- Foundations for the AHU-1 week of 04/06
- Drywall complete
- Tape and Sanding Worship Space in progress
- Primer Coat of Paint in the Classrooms/Office
- Ceiling Grid being installed in classrooms/offices
- Electrical devices and light fixtures are going in the classrooms/office
- Roof top units are being set.
- Altar was poured last week
- Stained Glass Windows – One Large Window and One Smaller Window today, 45% complete, The balcony is done, all but the vent windows that were on the west side and some of the small windows that were on the east side. (pick new locations)