April 9th Update

  • Brick and Stone is complete except for the piers
  • Shingles are complete except for the canopies
  • Windows are installed except for the round windows over the altar
  • EFIS is starting – Water Proofing coat done 04/09
  • Underground Storm Drainage
  • Piers for the columns are being formed at main entrance
  • Canopy Drop off is being framed
  • Site paving will start week of 04/13 weather permitting
  • Foundations for the AHU-1 week of 04/06
  • Drywall complete
  • Tape and Sanding Worship Space in progress
  • Primer Coat of Paint in the Classrooms/Office
  • Ceiling Grid being installed in classrooms/offices
  • Electrical devices and light fixtures are going in the classrooms/office
  • Roof top units are being set.
  • Altar was poured last week
  • Stained Glass Windows – One Large Window and One Smaller Window today, 45% complete, The balcony is done, all but the vent windows that were on the west side and some of the small windows that were on the east side. (pick new locations)