- Brick and Stone is complete except for the piers
- Shingles are complete except for the canopies
- Windows are installed except for the round windows over the altar
- EFIS is starting – Water Proofing coat done 04/09
- Underground Storm Drainage
- Piers for the columns are being formed at main entrance
- Canopy Drop off is being framed
- Site paving will start week of 04/13 weather permitting
- Foundations for the AHU-1 week of 04/06
- Drywall complete
- Tape and Sanding Worship Space in progress
- Primer Coat of Paint in the Classrooms/Office
- Ceiling Grid being installed in classrooms/offices
- Electrical devices and light fixtures are going in the classrooms/office
- Roof top units are being set.
- Altar was poured last week
- Stained Glass Windows – One Large Window and One Smaller Window today, 45% complete, The balcony is done, all but the vent windows that were on the west side and some of the small windows that were on the east side. (pick new locations)
April 9th Update