January 6th Update

  • Permanent power was installed last week.
  • Temporary winter protection over windows and doors of the Parish Hall, Classrooms and Office space is in place.
  • Winter Heat was turned on Friday, January 2nd.
  • Framing of the West wall of the Worship Space continues.
  • 2/3 of the roof decking and roof angle is done on Worship Space.
  • Window Blocking for the stained glass windows is complete.
  • Exterior wall framing and trusses are complete on Gathering Space.
  • Metal roof deck will start today on Gathering Space.
  • Exterior sheathing should start back up today on Worship/Gathering.
  • Finishing the framing of the crickets and dormers on Parish Hall, then the metal deck can be completed.
  • Roof decking will start today on Gathering Space.
  • Nailable roof insulation is on going.
  • Classrooms and offices are done and felt paper is on.
  • The North side of the Parish Hall done, waiting for the dormers to complete.
  • Flat roof areas will start today.
  • Above Ceiling Mechanical and Electrical is on going.