- Permanent power was installed last week.
- Temporary winter protection over windows and doors of the Parish Hall, Classrooms and Office space is in place.
- Winter Heat was turned on Friday, January 2nd.
- Framing of the West wall of the Worship Space continues.
- 2/3 of the roof decking and roof angle is done on Worship Space.
- Window Blocking for the stained glass windows is complete.
- Exterior wall framing and trusses are complete on Gathering Space.
- Metal roof deck will start today on Gathering Space.
- Exterior sheathing should start back up today on Worship/Gathering.
- Finishing the framing of the crickets and dormers on Parish Hall, then the metal deck can be completed.
- Roof decking will start today on Gathering Space.
- Nailable roof insulation is on going.
- Classrooms and offices are done and felt paper is on.
- The North side of the Parish Hall done, waiting for the dormers to complete.
- Flat roof areas will start today.
- Above Ceiling Mechanical and Electrical is on going.
January 6th Update